Ex Store fuel  - Borgo Virgilio (MN)

In this project BSA replaced other company


N.  16 tanks with capacity from 25 to 1.000 m3
containing mineral oils: gasoline, diesel oil and fuel
  • Text Hover
  • Text Hover
  • Text Hover
  • Text Hover
CONTAMINATION
Contamination of soils and groundwater.

CONTAMINANTS
Hydrocarbons (C≤12 and C>12) – BTEX – MTBE - ETBE.

ACTIVITY 
> Implementation of the measures additional of characterization.
> Direct management of the entire procedure:
     •    Characterization Plan and Technical Report;
     •    Final Project of Reclamation;
     •    Final Technical Report;
     •    Planning and execution of all planned activities;
     •    Assistance of during Conferences of Services;
> Execution of reclamation: on site treatment of the soil and in situ treatment of the groundwater with direct push system.
> Monitoring. 
> Coordination and execution of all activities carried out jointly with the Authorities.  
> Testing jointly with ARPA: 2 years monitoring. 

NO Disposal of contaminated soil.
NO Realization of complex and costly installations.
DURATION
Thirty-six months

COSTS
Saving of 50% compared to
the other techniques.

FINAL TEST

  • Testing jointly with ARPA, Section of Mantova. Achievement of the goals of reclamation: Table 1B (soil) and 2 (groundwater), Allegato 5 Parte Quarta Titolo V, D.Lgs.152/06